About Us » Campus Construction News

Campus Construction News

Flagpole installed in its new home, concrete work, insulation happened, windows were sealed and drywall has begun! 
 
outside
flag pole
October 11
 
New cafeteria windows are in! Since steel walls, electrical, plumbing are also done, after doors go in next week, the insulation, drywall and finish in the interior of the new caf can commence.
 
oct 11 update
September 27
Interior walls going up, but some weeks it’s the “little” stuff that seems like such progress! This week the 6 parking lot lights were re-installed, this time with LEDs that don’t need to be so tall to shed a lot of light. 
lights lights
September 20
The brickwork is done! Interior walls are going up and the lawn has begun to be leveled in preparation for landscaping. 
sept 20 brick facade
sept 20 interior wall studs
sept 20 lawn leveling
August 30
Drones shots from the past week show the progress that's taking place outside; now that school is in session with functional remodeled spaces, the focus has almost completely shifted to the cafeteria and entry addition. We remain on target for completion before the end of the calendar year.
Aug. 16
 
There's still plenty left to do with this construction project (i.e., everything that is an "addition"), but our existing cafeteria, the lobby restrooms, and a functional (but not finished) office space were good to go for freshman orientation.
We thank God for the cooperation of patient and helpful faculty and staff, and the perseverance and skill of our project manager, site supervisor and all the subs who have gotten us to this point
Aug 9 update! 
 
Aug 9
Aug 2 update
 
Aug 2
July 26
Take a look at the transformation from the air this week! Join us in both thanks for current progress and prayers for on-time material delivery and full crew availability for weeks to come. 
 
April-July now & then
July 12
Time for then and now pics:
mar 20
july 11
Great news from our Operations Director that demo crews are finished and the focus is now reconstruction.  This week? Boys' lobby bathroom has new tile! Masons have completed a lot of patchwork, infilling, and have begun exterior walls -- it's looking up for sure! The cement is in for the new lawn monument. Ceiling grid is well on its way to being installed, lights have arrived. We are on schedule to have the original building area remodels complete by the first day of school. New entry, office area, and cafeteria space are scheduled for completion in December. Exciting!
caf
monument
interior
As part of this week's work, the original 1962 cornerstone was carefully removed—and we found a surprise! Inside was a sealed copper time capsule.
 
capsule
June 7
The first week of June was week 2 of demo.
caf demo
May 31
Lots of interior demo happening! 
bathrooms
office
The week of May 20-24 saw some facade demo in between the raindrops ⛈
May 24 demo
 
As of Friday, May 17, the addition footprint is complete.
start of backfill
footings backfill
Thursday, April 25 2024: footings are poured
 
april 25
News release  from week of April 15, 2024:

Lakeside Lutheran breaks ground for addition

LAKE MILLS – Lakeside Lutheran High School broke ground on a building expansion and renovation on April 8. The project includes a more prominent main entrance and front lawn monument, a cafeteria and front office renovation and expansion, as well as renovated lobby restrooms. Existing interior renovations are expected to be complete in time for the start of the upcoming school year; the entire project, including the expanded cafeteria space and a renovated main entry, has a December 2024 planned completion date.


The school held a small ceremonial groundbreaking on Wednesday, April 10, when administration, student and governing board representatives, as well as reps from general contractor Design 2 Construct (D2C), and major contributor Twice is Nice Resale Store, gathered to ask for God’s blessing on the undertaking. At the groundbreaking, Principal Don Schultz reminded those gathered of the words of Solomon in Psalm 127, “Unless the Lord builds the house, the builders labor in vain.”


“This project involves an expansion of our cafeteria to resolve an issue of overcrowding,” explains Executive Director Kirk DeNoyer. “It will almost double its size, pushing cafeteria space south out to the current sidewalk. Along with that, we're extending the kitchen to have a place for parent and community groups to host meals at events.” DeNoyer also refers to a common misperception, that the more eastern front doors are often thought to be the main entrance. “A new prominent front entryway means when visitors come to campus, they know exactly where to go. We want to give them a great first impression,” he says.


This project is the second phase of a renovation and upgrade plan called “Free to Act.” This campaign began in 2021 after the last mortgage was satisfied and the school became debt-free. Planners began reviewing the condition of the building and grounds with a goal to achieve as many as possible without the need for a new mortgage. 


After faculty and staff input and governing board discussion, school administration developed a multi-year, three-phase plan. “Free to Act Phase 1” ran from 2021-2023 and included a faculty workroom update, locker room renovation, media center/study hall remodel, improved visitor seating for the outdoor competition field, a West Gym renovation, and videography studio remodel. Together these cost just over $1.2 million and were successfully completed by 2023 without a loan. The current project, “Free to Act Phase 2,” with planning begun in 2023, carries a $3.5M cost, with 80% secured through private donations prior to groundbreaking.

 

 
From e-news April 9, 2024:
DO NOT exit main doors
 
 
Email sent to students Tuesday, April 2 from Assistant Principal Dorn:
 
only staff parking on street

 

Parking

Many of you may have already heard, but the closing of our front parking lot is happening a few days earlier than expected. Fencing will be installed Wednesday, April 3.  This is happening to prepare for the actual construction to begin the following Monday.

This means that parking will be at a premium.  Students will still be expected to park in the parking lots and not on a street.  A few Staff/Faculty individuals have agreed to park on Woodland Beach to ease the crowding and leave enough room for students and the remainder of the staff.  (See attached Picture for available parking and traffic flow)

Please, do not park in the visitor parking area. There are only a few spaces left that need to be saved throughout the day. (look for reserved signs) Do not park in the first row of parking spaces by the bus barn. You will be asked to move if you park in either of these reserved spots. 

School Entrances

The normal front entrance will be closed due to construction as well. During the school day you will need to use the other double door entrance at the front of the building near the atrium. There is a new doorbell that you will have to use to gain entry. Follow the posted directions as to how to use it. It's a touch and swipe up access panel. 

Whomever is on attendance duty for the day will spend the first 2 - 3 hours of the day with a mobile desk down by the new entrance and can let you in. After that, there is a video camera that the office will greet you through and then you will be buzzed in. The front office is still the main hub for student activity. All day-to-day needs (absence sheets, illness, tardies....) will still be taken care of in the office and students still need to check in with the office if they arrive late to school. 

Administrative Offices

 

Some front offices will be vacated because of the construction. If you can't find someone you are looking for, just ask the front office staff and they will help you find the person you are looking for.

_________________________________
_________________________________
 
While the construction begins April 8, a low-key groundbreaking ceremony will happen Wednesday, April 10 at 1:30 pm. While it is not a private event, it will be a brief recognition that has not been publicized widely. 
_________________________________
 
Update March 25: The cafeteria expansion and main entry remodel (Phase 2 of our Free2Act plan) is expected to begin Wednesday, April 3 when the main office doors will be inaccessible for several months. The atrium entrance (by the big blue cross) will be the main entrance until construction is complete, and parking and drive lanes will be affected while construction equipment is parked in the front. See the image above for new traffic patterns in the front of school. Please contact Executive Director Kirk DeNoyer ([email protected]) with questions about changes to campus and parking.